Google has suspended construction work on a major data centre project in Belgium after regional authorities ordered the company to stop building over a dispute concerning planning permission. The project, located in Wallonia near the city of Charleroi, has become the centre of a legal and environmental controversy involving construction approvals, water consumption and the infrastructure demands of artificial intelligence.

The US technology giant confirmed on November 28, 2026, that it had halted work following instructions from local authorities and was awaiting further guidance. Belgian officials allege that construction continued without the necessary approval for changes to the original project. Google, however, maintains that it holds valid permits for parts of the development and has challenged the authorities’ decision in court. The dispute highlights the growing regulatory challenges facing technology companies building infrastructure for the AI industry.

Why Google Halted Construction in Belgium

The controversy centres on a data centre campus in the Wallonia region of southern Belgium, near Charleroi. The development occupies a 50-hectare business park built on the site of a former coal mine.

Belgian regional authorities ordered Google to suspend construction after inspections raised questions about whether the ongoing work complied with the project’s approved planning permissions.

Nicolas Yernaux, spokesperson for the Wallonia regional government, described the alleged violation as a major offence involving the construction of a building covering approximately three hectares without the required authorisation.

Regional officials said inspectors found that the building was nearly complete, with its structural work already finished, despite the disputed permit having been revoked.

Approximately 300 workers were reportedly affected by the stop-work order.

Google subsequently confirmed that it had suspended construction in accordance with the authorities’ instructions.

The company said it had operated in Belgium for more than 15 years and remained committed to complying with local regulations. It also said it would continue discussions with government officials while awaiting additional guidance.

What Triggered the Planning Permission Dispute?

The disagreement began when Google sought to modify the original design of its Belgian data centre development.

The company’s initial 2024 planning permission covered three smaller data centre buildings using air-based cooling systems.

However, Google submitted an application in 2025 to change the development plan. The proposal involved combining two of the planned facilities into one larger building and replacing the original air-cooling arrangement with a water-based cooling system.

The revised design proposed drawing water from the nearby River Sambre to cool the data centre infrastructure.

Regional authorities initially approved the modifications in April 2026. However, the approval faced objections from residents and environmental organisations concerned about the project’s water requirements.

In August 2026, Wallonia Infrastructure Minister François Desquesnes revoked the modified permission.

The decision was linked to concerns about the availability of sufficient water from the river, particularly as climate change and recurring dry conditions increase pressure on local water resources.

Google challenged the decision before Belgium’s Council of State, the country’s highest administrative court.

The dispute has remained unresolved, creating uncertainty about which construction activities can legally continue at the site.

Water Consumption Becomes a Major Environmental Concern

The proposed cooling system has become one of the most contentious aspects of the project.

According to reports about the revised application, Google’s proposed water-based cooling arrangement could draw approximately 600 cubic metres of water per hour from the River Sambre.

<text highlight=”none”></text>

That is a substantial water requirement for a facility located in a region where authorities have expressed concerns about drought and future water availability.

Data centres require cooling systems to prevent servers and other computing equipment from overheating. As facilities become larger and handle more demanding workloads, managing the heat generated by computing infrastructure becomes increasingly important.

Traditional air-cooling systems use mechanical equipment to circulate and cool air. Liquid-based cooling systems can transfer heat more efficiently in certain high-density computing environments, making them attractive for facilities designed to operate large numbers of AI processors.

However, water-based cooling can introduce additional environmental considerations, depending on the technology used, water sourcing and whether water is consumed or recirculated.

For Google’s Belgian project, the proposed change raised questions about whether the River Sambre could reliably support the facility’s requirements during periods of water stress.

The authorities ultimately withdrew approval for the modified design, prompting the ongoing legal challenge.

Greenpeace Opposes Google’s Data Centre Expansion

Environmental organisation Greenpeace Belgium has also criticised the project.

The organisation published a report containing drone footage that it said showed construction continuing despite the absence of the necessary modified planning permission.

Greenpeace argued that large data centres could place additional pressure on local electricity and water resources, particularly as demand for AI computing increases.

Joeri Thijs of Greenpeace Belgium said continuing construction without the required permit demonstrated insufficient respect for environmental concerns, local residents and the law.

The organisation has also raised broader concerns about the environmental footprint of energy-intensive data centre infrastructure.

The opposition reflects a wider debate across Europe about whether governments should approve increasingly large computing facilities without adequately considering their long-term impact on local resources.

For communities, the concerns extend beyond the construction phase. Once operational, large data centres can require substantial electricity supplies, cooling infrastructure, water management systems and supporting grid capacity.

Google Says Some Existing Permits Remain Valid

Google has disputed the suggestion that its entire Belgian development lacks planning permission.

According to the company’s explanation reported by The Brussels Times, several permits covering the overall data centre campus remain valid and are not being challenged.

Google said it began construction based on permission granted for modifications to the project in April 2026. That modified permission was subsequently annulled in August.

The company has argued that some activities continued under the original authorisation and that work carried out after the revocation was also intended to maintain the site’s safety and security.

This distinction is important because the dispute concerns the legality of particular construction activities and changes to the original project, rather than a definitive finding that every part of Google’s data centre campus is unauthorised.

Google has appealed the revocation, and the company is awaiting the outcome of the legal proceedings.

A hearing before the Council of State is expected on January 7, 2027. The decision could clarify the status of the modified planning permission and determine how the project can proceed.

Why the Dispute Matters for the AI Industry

Google’s Belgian construction halt comes at a time when technology companies are investing billions of dollars in data centre infrastructure.

The growth of generative AI has increased demand for specialised computing facilities equipped with advanced processors, high-speed networking and sophisticated cooling systems.

Google is expanding its infrastructure to support services such as Gemini, Google Cloud and other AI-powered products. Similar investments are being made by Microsoft, Amazon and other technology companies.

However, the expansion is increasingly creating competition for local resources.

Infrastructure challengeWhy it matters
Electricity consumptionLarge AI facilities require substantial and reliable power supplies
Water availabilitySome cooling systems depend on local water resources
Land useData centre campuses require large areas and supporting infrastructure
Grid capacityNew facilities can increase pressure on regional electricity networks
Environmental permissionsProjects must comply with planning and environmental regulations

European governments are under pressure to balance the economic benefits of AI infrastructure with environmental protection and local community interests.

Data centres can generate investment, create construction activity and support digital services. However, their resource requirements mean that planning decisions increasingly involve questions about long-term sustainability.

The Bigger Picture

The Belgian dispute demonstrates that access to computing infrastructure is becoming a regulatory and environmental issue, not just a technology investment decision. As AI models become larger and businesses deploy them more widely, the demand for data centres will continue to put pressure on electricity networks, water resources and land availability.

For Google, the immediate challenge is resolving the planning dispute and establishing which parts of its development can legally proceed. For the wider technology industry, the case shows that securing land and financing is no longer enough. Companies must also demonstrate that their infrastructure plans are compatible with local environmental conditions and regulatory requirements.

Looking Ahead

The next important development will be the expected January 7, 2027, court hearing concerning Google’s appeal against the revocation of its modified planning permission. The outcome could determine whether the company can proceed with its revised cooling and construction plans or must reconsider the design. Until then, the suspended construction work leaves the project’s immediate timeline uncertain.

The controversy could also influence how other European authorities evaluate large AI data centre proposals. Governments may demand more detailed assessments of water consumption, cooling technology and environmental impact before approving new developments. As competition for AI computing capacity intensifies, the ability to secure regulatory approval and sustainable infrastructure could become just as important as access to advanced chips.