A nearly 90% increase in Common Area Maintenance (CAM) charges at The Westerlies, a prominent residential township in Sector 108 along the Dwarka Expressway in Gurugram, has triggered a dispute between homeowners and the project’s builder. Residents staged a peaceful demonstration against developer Experion Developers and its facility maintenance agency, Mainage Facility Management, issuing a 15-day ultimatum for a time-bound resolution before pursuing formal legal and regulatory action.
Key takeaways
- 90% fee revision: Common Area Maintenance charges at the Sector 108 township jumped from ₹10 to ₹19 per unit measurement, marking a near-doubling of monthly recurring upkeep overheads for homeowners.
- Protests over deficient amenities: Residents and the Resident Welfare Association (RWA) allege that the developer raised fees arbitrarily while basic promised infrastructure—including clubhouse facilities, completed green zones, paved connectivity, and dedicated security protocols—remains incomplete or sub-par.
- 15-day ultimatum issued: The RWA has given Experion Developers and Mainage Facility Management a 15-day deadline to produce a written, time-bound action plan addressing service deficiencies and auditing financial cost allocations.
- Highlighting recurring ownership costs: The standoff illustrates a growing issue in large planned developments: buyers often budget for unit purchase prices and registration taxes, only to face steep post-possession maintenance increases before infrastructure handovers to RWAs take place.
- Legal and RERA recourse: If negotiations stall, homeowners plan to escalate the dispute before the Haryana Real Estate Regulatory Authority (H-RERA) and consumer disputes redressal forums to seek third-party forensic audits of CAM accounts.
The dispute: What happened at The Westerlies
The conflict centers on The Westerlies, an expansive plotted and villa township developed across more than 100 acres in Gurugram’s Sector 108, situated near the Dwarka Expressway corridor.
Over the weekend, homeowners gathered to hold peaceful demonstrations following formal communication that base CAM rates were being raised from ₹10 to ₹19—an effective increase of 90%.
THE WESTERLIES CAM FEE DISPUTE SNAPSHOT:
[ Base CAM Charges Prior to Revision ] ────► ₹10
│
▼
[ Revised Fee Imposed by Management ] ─────► ₹19
│
▼
[ Net Cost Escalation ] ───────────────────► +90% Jump in Monthly Recurring Upkeep
│
▼
[ Core Resident Grievances ] ──────────────► Incomplete Club & Park Infrastructure
- Gaps in Security & Horticultural Care
- Absence of Audited Cost-Breakdown Justification
Residents voiced frustration that while recurring costs are escalating rapidly, the physical experience on the ground fails to reflect premium charges:
- Incomplete common amenities: Several promised township features—including full recreational clubhouse facilities, operational sports courts, and fully landscaped green zones—remain partially executed or delayed despite years of resident occupancy.
- Substandard basic upkeep: Protesters cited inconsistent horticulture management, irregular cleanliness along internal township roads, and security coverage gaps across multiple entry gates.
- Lack of financial transparency: The RWA argued that steep revisions must be preceded by open-book financial disclosures, demonstrating actual operational vendor cost increases rather than unilateral administrative notices.
Anatomy of CAM charges: Why maintenance fees escalate
The dispute at Sector 108 highlights how Common Area Maintenance (CAM) functions in modern gated societies and integrated townships:
What does CAM actually cover?
CAM charges are recurring monthly or quarterly levies collected to operate and preserve shared property infrastructure outside private apartment walls:
- Common Area Power & DG Backup: Operating streetlights, water-lifting pumps, central sewage treatment plants (STPs), and diesel generator (DG) power backup during electricity outages.
- Security & Access Control: Staffing guard shifts, automated RFID boom barriers, CCTV network maintenance, and perimeter patrolling.
- Housekeeping & Horticulture: Daily road sweeping, garbage collection, waste segregation, and maintaining parks and green belts.
- Mechanical & Electrical Upkeep: Preventative maintenance contracts for lifts, fire suppression systems, and central water treatment units.
- The Sinking Fund: A regulatory capital reserve accumulated for major long-term asset replacements (such as road resurfacing, building repainting, or pump overhauls).
| CAM Expense Component | Primary Operational Cost Driver | Typical Share of Total Budget |
| Security & Surveillance | Multi-shift guard deployment across multiple gates | 25% – 35% |
| Power & Backup Utilities | Common electricity + high diesel rates for DG run-time | 20% – 30% |
| Housekeeping & Waste | Janitorial labor, waste management, sanitation gear | 15% – 20% |
| Horticulture & Green Belts | Landscaping crews, seasonal flora, irrigation water | 10% – 15% |
| Equipment AMCs & Repairs | Annual contracts for STPs, fire pumps, electrical panels | 10% – 15% |
Why developer-managed maintenance creates friction
In many Indian developments, particularly newly occupied sectors along the Dwarka Expressway and New Gurgaon, maintenance remains under the control of the developer or its captive facility management subsidiary for several years following initial possession.
This arrangement frequently leads to buyer-developer friction:
- Asymmetric pricing control: Homebuyers have limited leverage over operational contracts. Developers often select their own facility management arms or captive vendors without competitive open-market bidding.
- Delayed RWA Handover: As long as a township has pending construction phases or unsold inventory, developers retain administrative control, delaying the formal transfer of maintenance operations and audited sinking funds to an elected RWA.
- The “low-ball” handover trap: Developers occasionally subsidize maintenance fees during the initial marketing and possession phase to make properties appear affordable. Once occupancy reaches critical mass, the facility management company hikes rates abruptly to match actual operating overheads, catching homeowners off guard.
Regulatory and legal remedies: What the law says in Haryana
Under Haryana’s real estate governance framework—governed by the Real Estate (Regulation and Development) Act (RERA), 2016 and the Haryana Apartment Ownership Act, 1983—residents have defined legal avenues to contest arbitrary maintenance hikes:
LEGAL RECOURSE PIPELINE FOR DISPUTED CAM CHARGES:
[ RWA Demands Audited Financials & Vendor Contracts from Builder ]
│
▼
[ 15-Day Resolution / Conciliation Window ]
│
┌──────────────────────┴──────────────────────┐
▼ ▼
[ Escalation to H-RERA Gurugram ] [ Consumer Disputes Forum (DCDRC) ]
- Petitions for Forensic CAM Audit - Files Complaints for Deficiency in Service
- Challenges Unilateral Fee Changes - Seeks Injunction Against Arbitrary Dues Cut-off
- Demands Formal Handover to RWA - Demands Compensation for Non-Delivery of Amenities
- H-RERA Interventions on Transparency: H-RERA authorities in Gurugram have established precedents requiring developers to maintain open-book transparency in CAM accounts. Developers are legally prohibited from profiting off maintenance operations—CAM collections must operate on a cost-to-cost basis.
- Third-Party Forensic Audits: If a developer imposes a steep fee increase without consensus, RWAs can petition H-RERA to order an independent chartered accountant to conduct a forensic audit of the society’s operational expenditures.
- Essential Services Protection: Developers and facility management agencies are barred under judicial rulings from disconnecting essential utilities—such as drinking water supply, prepaid electricity meters, or access lifts—as a coercive tool to enforce disputed maintenance hikes.
Buyer checklist: What to verify before purchasing in a gated township
The 90% fee revision at Sector 108 serves as a cautionary case study for prospective property buyers across urban centers. When evaluating purchases in large planned communities, real estate advisors recommend evaluating recurring maintenance structures alongside square-foot capital rates:
- Examine the builder-buyer agreement (BBA): Scrutinize specific clauses governing CAM escalations, the formula for calculating rate increases, and the timeline for handing over maintenance control to an elected RWA.
- Audit the society sinking fund: Verify whether the developer maintains a segregated bank escrow account for the accumulated sinking fund and Interest-Free Maintenance Security (IFMS), ensuring capital reserves are not absorbed into general corporate funds.
- Track phased occupancy numbers: Large townships with sprawling acreage but low early occupancy face higher per-unit maintenance burdens, as fewer residents share the high fixed cost of running extensive security, road lighting, and landscape irrigation.
- Review GST thresholds: Remember that maintenance payments exceeding ₹7,500 per member per month attract an additional 18% Goods and Services Tax (GST), adding a substantial tax layer onto already elevated base CAM charges.
What could happen next
- Action-plan deadline: The 15-day timeline set by The Westerlies RWA will expire in mid-October 2026, requiring Experion Developers and Mainage Facility Management to present a detailed operational timeline and cost ledger.
- Conciliation or H-RERA petition: If the developer fails to roll back or rationalize the revision, the RWA is expected to file a formal petition before the Haryana Real Estate Regulatory Authority (H-RERA) bench in Gurugram seeking an immediate stay on the 90% increase.
- Handover roadmap talks: Discussions may accelerate regarding a phased transfer of civic services and internal security directly to the RWA, establishing an elected committee to renegotiate vendor contracts through open tenders.
Frequently asked questions
What are CAM charges in real estate?
Common Area Maintenance (CAM) charges are monthly or quarterly fees paid by property owners in gated societies and townships to cover the operating costs of shared spaces, including 24/7 security, common lighting, lift upkeep, diesel generator backup, landscaping, and waste management.
Why did residents protest at The Westerlies in Gurugram?
Residents of The Westerlies in Sector 108 protested against a 90% hike in CAM fees (from ₹10 to ₹19 per unit), arguing that the developer implemented the increase unilaterally while basic promised facilities, clubhouse amenities, and standard maintenance services remain incomplete.
Can a developer arbitrarily increase maintenance charges?
No. Under RERA and apartment ownership laws, maintenance fees must be charged on a cost-recovery basis without profit markups. Developers must maintain audited accounting records and demonstrate that rate increases reflect verifiable increases in vendor expenses or municipal utility costs.
What can residents do if a developer imposes an unfair maintenance hike?
Homeowners and RWAs can demand audited expense ledgers, issue legal notices for deficiency of services, and file formal petitions before H-RERA or consumer dispute forums. Regulatory authorities can order third-party audits and direct developers to hand over maintenance management to the RWA.