India has delayed its ambitious ₹18,100 crore programme to build a domestic advanced-chemistry-cell battery manufacturing ecosystem, with beneficiaries facing setbacks in setting up plants and achieving production milestones. The delay comes as manufacturers continue to face technology, equipment, skilled manpower and supply-chain constraints, highlighting the challenges involved in reducing India’s dependence on imported battery cells.

The Production Linked Incentive (PLI) programme, approved in 2021, was designed to establish 50 GWh of domestic advanced chemistry cell (ACC) manufacturing capacity. However, official government data show that only 1 GWh of the 40 GWh capacity awarded to four companies had been installed as of March 2026. By June 2026, the programme was still facing implementation delays, with Ola Electric remaining the only beneficiary to have started commercial-scale cell production. :contentReference[oaicite:0]{index=0}

₹18,100 Crore Battery PLI Scheme Faces Delays

The National Programme on Advanced Chemistry Cell (ACC) Battery Storage was approved in May 2021 with a total government outlay of ₹18,100 crore.

The scheme aims to establish 50 GWh of domestic ACC manufacturing capacity and reduce India’s dependence on imported battery cells. Of the targeted 50 GWh, 40 GWh has been awarded to four beneficiary companies through two rounds of bidding. :contentReference[oaicite:1]{index=1}

The programme provides financial incentives to manufacturers based on factors including battery sales, quoted subsidy per kWh and the level of domestic value addition achieved.

India’s Battery PLI Scheme At A Glance

ParameterDetails
SchemePLI for Advanced Chemistry Cell Batteries
ApprovalMay 2021
Total outlay₹18,100 crore
Target capacity50 GWh
Capacity awarded40 GWh
Beneficiary companies4
Capacity installed as of March 20261 GWh
Domestic manufacturing goalReduce battery import dependence
Scheme structureProduction-linked incentives

The gap between the 50 GWh target and the capacity actually commissioned demonstrates the scale of the implementation challenge.

Only 1 GWh Of Awarded Capacity Was Installed

The latest government data available in March 2026 showed that only 1 GWh of the 40 GWh awarded capacity had been installed.

Ola Cell Technologies accounted for that 1 GWh, while ACC Energy Storage, Reliance New Energy Battery Storage and Reliance New Energy Battery had yet to report installed capacity at that point. :contentReference[oaicite:2]{index=2}

Beneficiary-Wise Progress

CompanyCapacity AwardedCapacity Installed*
ACC Energy Storage Pvt. Ltd.5 GWh0 GWh
Ola Cell Technologies Pvt. Ltd.20 GWh1 GWh
Reliance New Energy Battery Storage Ltd.5 GWh0 GWh
Reliance New Energy Battery Ltd.10 GWh0 GWh
Total40 GWh1 GWh

*Government data reported as of March 2026.

This means only about 2.5% of the 40 GWh capacity awarded under the scheme had been installed at that stage.

Capacity Progress

Targeted national capacity
50 GWh
██████████████████████████████████████████████████

Awarded capacity
40 GWh
████████████████████████████████████████

Installed capacity
1 GWh

The difference shows why the government has faced pressure to extend timelines for the programme.

Why The Battery Manufacturing Programme Is Delayed

Battery-cell manufacturing is significantly more complex than assembling battery packs from imported cells.

Manufacturers need specialised equipment, technical expertise, upstream materials and access to advanced cell technology.

The government has identified several challenges facing beneficiaries, including shortages of skilled manpower, imports of critical equipment and machinery, and the non-availability of upstream components. :contentReference[oaicite:3]{index=3}

Major Bottlenecks

ChallengeImpact
Skilled manpower shortageSlower plant commissioning
Imported equipmentLonger procurement and installation timelines
Specialist techniciansDelays in commissioning machinery
Upstream component shortagesLimits local production
Battery technology accessMakes localisation more difficult
Supply-chain dependenceCreates external vulnerabilities

These constraints have made it difficult for companies to move quickly from investment announcements to commercial-scale cell production.

China Remains A Major Technology And Equipment Challenge

India’s battery ambitions are also being affected by its dependence on China-linked technology and equipment supply chains.

Battery manufacturers need specialised machinery and technical support for cell-production lines. Business Today reported that manufacturers have faced difficulties obtaining equipment and bringing qualified technicians to India for installation and commissioning. :contentReference[oaicite:4]{index=4}

The problem is particularly important because India wants to develop an indigenous battery ecosystem while much of the global battery supply chain remains concentrated in China.

Battery Manufacturing Dependency

China-linked ecosystem

Specialised equipment

Technical installation

Cell-production commissioning

Domestic battery manufacturing

If access to equipment, technicians or technology is delayed, the commissioning of Indian plants can also be pushed back.

Amara Raja Highlights Technology Challenges

Amara Raja Energy & Mobility, which is developing its own battery-cell capabilities outside the PLI scheme, has also highlighted the difficulties involved in localising battery production.

The company said its proposed partnership with China’s Gotion had not progressed because of geopolitical issues and that it was therefore developing much of its technology in-house. :contentReference[oaicite:5]{index=5}

Amara Raja plans to commission an initial 2 GWh battery-cell facility and eventually add capacity in phases.

The company has also invested about $100 million in a research and engineering centre and a qualification plant as part of its effort to develop cell capabilities internally. :contentReference[oaicite:6]{index=6}

Amara Raja’s Battery Plans

ParameterPlan
Initial gigafactory capacity2 GWh
Planned eventual capacity16 GWh
Target horizon2030-31
R&D and qualification investment~$100 million
Initial chemistryNMC lithium-ion
Future chemistriesNMC, LFP and others

The company’s experience illustrates the wider difficulty Indian companies face in building cell manufacturing capabilities from the ground up.

India Still Depends Heavily On Imported Battery Cells

Despite the government’s battery-manufacturing programme, domestic demand continues to be met largely through imports.

The Ministry of Heavy Industries said in March that the PLI ACC programme was specifically designed to reduce India’s dependence on imported ACCs, but domestic demand was still being met largely through imports. :contentReference[oaicite:7]{index=7}

This creates a strategic challenge because India’s electric-vehicle market is expanding rapidly.

India’s EV Adoption Is Rising

Official government data show that EV penetration increased from 0.7% of vehicle sales in FY2020 to 8.2% in FY2026, supported by schemes including FAME-II and PM E-DRIVE. :contentReference[oaicite:8]{index=8}

Financial YearEV Penetration
FY2019-200.7%
FY2025-268.2%
Increase7.5 percentage points

As electric-vehicle adoption grows, demand for battery cells is expected to rise as well.

This makes the delay in domestic cell manufacturing particularly significant.

Battery PLI Has Already Attracted ₹3,237 Crore Of Investment

Although capacity commissioning has been slow, the scheme has helped trigger investment in the broader battery ecosystem.

As of December 31, 2025, the four PLI beneficiaries had reported cumulative investment of ₹3,237 crore and employment generation of 1,118 people. :contentReference[oaicite:9]{index=9}

Investment And Employment

IndicatorReported Figure
Cumulative investment₹3,237 crore
Direct employment1,118
Capacity awarded40 GWh
Capacity installed1 GWh

The government says the scheme has also encouraged companies outside the PLI programme to announce additional battery-cell manufacturing projects.

Companies Outside The PLI Scheme Have Announced 178 GWh

At least 10 manufacturers outside the PLI applicants have announced cumulative battery-cell capacity of about 178 GWh over the next five years, according to the Ministry of Heavy Industries. :contentReference[oaicite:10]{index=10}

This suggests that the government’s battery policy has had a broader signalling effect beyond the four companies directly receiving PLI incentives.

India’s Announced Battery Capacity

PLI-awarded capacity
40 GWh

Other announced capacity
178 GWh

Combined announced/awarded
218 GWh

However, announced capacity should not be confused with operational capacity. Actual production will depend on whether companies complete investment, equipment installation, qualification and commercial commissioning.

Reliance And Ola Are Central To The Plan

Two of the most prominent companies involved in the PLI programme are Reliance and Ola Electric.

Reliance has received a combined 15 GWh allocation across two entities, while Ola Electric has received the largest single allocation of 20 GWh. :contentReference[oaicite:11]{index=11}

Major PLI Allocations

Company / GroupCapacity Awarded
Ola Cell Technologies20 GWh
Reliance entities combined15 GWh
ACC Energy Storage5 GWh
Total40 GWh

Ola Electric has already begun commercial operations with battery-cell capacity, although its operating capacity remains well below its total PLI allocation. :contentReference[oaicite:12]{index=12}

The Scheme Requires Domestic Value Addition

The PLI programme is not designed simply to assemble imported battery cells.

Beneficiaries must progressively increase domestic value addition.

Under the framework, companies are required to achieve at least 25% value addition at the mother-unit level within two years of the appointed date and raise it to 60% within five years. :contentReference[oaicite:13]{index=13}

Domestic Value-Addition Requirement

StageMinimum Value Addition
Within 2 years25%
Within 5 years60%

This requirement is important because the government’s objective is to create an Indian battery manufacturing ecosystem rather than simply move battery assembly into the country.

Why Delays Matter For Electric Vehicles

Battery cells are one of the most expensive and strategically important components of an electric vehicle.

If India continues importing a large share of cells, EV manufacturers remain exposed to international prices, currency movements, shipping costs and geopolitical disruptions.

Local manufacturing could potentially improve supply-chain resilience while supporting domestic battery technology development.

Imported Vs Domestic Battery Supply

Imported cells

International supply chains

Currency + shipping + geopolitical risks

EV manufacturers

Domestic cells

Indian manufacturing ecosystem

Local supply chain

Potentially greater resilience

However, domestic production will need to become competitive on cost, quality and scale before it can significantly displace imports.

Battery Manufacturing Is Expanding Beyond PLI Beneficiaries

The government’s February 2026 update said at least 10 manufacturers had announced approximately 178 GWh of cumulative capacity outside the PLI programme.

That broader investment pipeline suggests India’s battery sector is developing even though the flagship PLI projects have encountered delays. :contentReference[oaicite:14]{index=14}

The emerging ecosystem also includes battery-material companies, recycling firms, pack manufacturers and technology providers.

This could eventually create a more integrated domestic supply chain.

India Wants To Build A Complete Battery Ecosystem

The government’s broader objective extends beyond cell manufacturing.

A competitive battery industry requires access to cathode materials, anodes, separators, foils, chemicals, recycling infrastructure and manufacturing equipment.

The Ministry of Heavy Industries said the PLI programme had already increased demand for components including cathode active materials, anode active materials and foils. :contentReference[oaicite:15]{index=15}

Battery Value Chain

Raw materials

Cathode materials
+
Anode materials
+
Electrolytes / separators

Cell manufacturing

Battery packs

Electric vehicles

Battery recycling

India’s current weakness is particularly pronounced in several upstream segments, making the development of a complete domestic ecosystem a longer-term challenge.

The Government Has Not Yet Fully Assessed Import Reduction

The Ministry of Heavy Industries said in a July 2026 parliamentary response that it had not conducted an assessment of the reduction in battery import dependence resulting from the programme. :contentReference[oaicite:16]{index=16}

This is significant because reducing import dependence is one of the main objectives of the PLI programme.

The government can therefore track capacity installation and investment, but the exact reduction in India’s battery-import dependence has not yet been formally assessed.

The Bigger Picture

India’s decision to delay its ₹18,100 crore homegrown battery manufacturing programme by two years highlights the difficulty of creating a domestic battery industry in a sector dominated by established global supply chains. The PLI scheme has targeted 50 GWh of capacity and awarded 40 GWh to four companies, but only about 1 GWh had been installed as of March 2026. :contentReference[oaicite:17]{index=17}

The delay does not mean India’s battery ambitions have stalled completely. Companies outside the PLI scheme have announced around 178 GWh of additional capacity, while EV adoption has increased sharply and domestic manufacturers are investing in technology and production capabilities. But the slow commissioning of PLI plants demonstrates that India still faces major challenges around technology, equipment, skilled labour, upstream components and supply-chain dependence. :contentReference[oaicite:18]{index=18}

Looking Ahead

The next two years will be critical for India’s battery-manufacturing ambitions. The government will need to ensure that PLI beneficiaries can obtain specialised equipment, close technology gaps, recruit skilled workers and build reliable domestic supply chains. Companies will also need to move from pilot and qualification lines to commercially viable gigawatt-scale production.

For India’s EV industry, faster domestic cell production could eventually reduce dependence on imports and strengthen the country’s position in the global clean-energy supply chain. But the real measure of the ₹18,100 crore programme will not be the amount allocated or the capacity announced; it will be the number of gigawatt-hours actually produced competitively in India and the extent to which that production replaces imported cells.

Get the day’s top stories in your inbox

One concise email. No spam, unsubscribe anytime.