The Maharashtra Forest Department has ordered an immediate halt to construction work on Adani Green Energy Limited’s 1,500 MW Tarali pumped-storage project in Satara district, citing the absence of prior approval from the National Board for Wildlife (NBWL). The order, issued on November 13, 2026, directs the project developer to stop all ongoing work until the required permissions are obtained and asks the company to explain the basis on which construction began.
The regulatory action has brought renewed attention to the project, which is also facing questions over a dramatic revision in its reported cost estimate. The project was originally listed at ₹5,675 crore in its environmental clearance documentation, but a subsequent company submission cited ₹56.75 crore. The difference has raised concerns about the calculation of contributions towards wildlife conservation. Adani Green has rejected allegations of wrongdoing and says the revised figure relates to preliminary surveys and site investigations rather than the full project cost.
Why Has Maharashtra Ordered a Stop-Work?
The Satara Forest Division issued the order after an inquiry found that construction activities had commenced without what the department considers mandatory prior approval from the National Board for Wildlife.
The project is located in Patan taluka of Satara district, an area connected to the ecologically sensitive Sahyadri landscape. Forest officials have raised concerns about the project’s location in relation to the deemed Eco-Sensitive Zone of the Sahyadri Tiger Reserve.
The department’s notice asks the company to:
- Stop all ongoing construction activities immediately.
- Submit a written explanation within three days of receiving the notice.
- Provide copies of all statutory approvals and project-related maps.
- Submit original or attested permissions for tree cutting at the project site.
The department has warned that failure to provide a satisfactory explanation and the required documents could lead to legal and punitive action under applicable forest and wildlife laws.
The order does not itself establish that the company has committed a criminal offence. It reflects the forest department’s position that construction began before the required wildlife approval was secured.
What Is the Adani Tarali Project?
The Tarali Pumped Storage Project is a proposed 1,500 MW energy-storage facility being developed by Adani Green Energy in Maharashtra’s Satara district.
The project is planned around the Tarali dam reservoir and covers approximately 150.74 hectares of non-forest land across four villages:
- Nivade
- Tondoshi
- Kalambe
- Jalu
Pumped-storage hydropower facilities store electricity by moving water between two reservoirs at different elevations.
When electricity is available in excess, the facility uses power to pump water from a lower reservoir to an upper reservoir. When demand increases, the stored water is released through turbines to generate electricity.
This makes pumped storage useful for balancing electricity supply and demand, particularly as renewable energy sources such as solar and wind become a larger part of the power mix.
Unlike conventional hydropower plants that primarily generate electricity from natural water flows, pumped-storage facilities can store energy and release it when required.
Why Is the Wildlife Clearance Disputed?
The central regulatory issue is whether the project obtained the necessary wildlife approval before construction activities began.
The Maharashtra Forest Department says prior NBWL approval was required because of the project’s location in an area associated with the Sahyadri Tiger Reserve’s deemed Eco-Sensitive Zone.
Adani Green, however, maintains that the project has received the necessary statutory permissions to begin construction.
The company has said that:
- The project does not involve forest land.
- No component falls within a notified protected area, according to its assessment.
- Environmental clearance was granted on February 11, 2025.
- The Maharashtra Pollution Control Board issued Consent to Establish on April 7, 2025.
- The wildlife-clearance process was initiated separately, with the relevant proposal submitted to the authorities.
The company also says its proposal for survey and investigation activities was submitted in January 2025 and subsequently recommended by the State Board for Wildlife. It maintains that the overall project proposal has been submitted to the NBWL and remains under consideration.
The disagreement therefore concerns the distinction between the permissions already obtained and whether a separate wildlife approval was required before construction could proceed.
The ₹5,675 Crore to ₹56.75 Crore Project Cost Controversy
The stop-work order follows a separate controversy over the project’s declared cost.
According to documents reported by The Indian Express, the project’s environmental clearance issued in February 2025 recorded an estimated cost of ₹5,675 crore.
However, a subsequent company submission in September 2026 cited a figure of ₹56.75 crore. The revised amount is one-hundredth of the earlier estimate.
The difference is significant because the amount payable towards wildlife conservation was linked to the project’s cost.
| Particulars | Original estimate | Revised figure |
|---|---|---|
| Project cost | ₹5,675 crore | ₹56.75 crore |
| Reported 4% conservation contribution | ₹227 crore | ₹2.27 crore |
| Initial 1% deposit | — | ₹56.75 lakh |
| Remaining 3% | — | ₹1.7075 crore |
Figures reported by The Indian Express. The revised amount and related contribution calculations are part of the ongoing controversy.
The Maharashtra Forest Department had earlier asked the company to deposit ₹227 crore towards the Sahyadri Tiger Reserve’s conservation and protection requirements, based on the original project estimate.
Following the revised submission, the state wildlife authorities accepted the ₹56.75 crore figure for the relevant clearance process and asked the company to deposit 1% of that amount, or ₹56.75 lakh. The remaining 3% was to be deposited after NBWL approval.
This change has prompted questions about why the cost figure changed so substantially and whether the revised amount was appropriate for calculating the conservation contribution.
Adani Green’s Response to the Allegations
Adani Green Energy has rejected allegations that it reduced the project’s cost estimate to lower its statutory conservation obligations.
The company says the ₹56.75 crore figure referred only to preliminary site investigations and survey activities. It argues that the amount was not intended to represent the total cost of constructing the 1,500 MW pumped-storage facility.
The company has also maintained that the project is situated on private, non-forest land and does not fall within a notified protected area or the notified buffer zone of the Sahyadri Tiger Reserve.
According to its statement, the environmental clearance and Consent to Establish were obtained before construction began. The company says the wildlife-clearance process was being pursued separately in accordance with the conditions attached to the project.
These are the company’s stated positions. The forest department’s stop-work order and the questions surrounding the cost submission remain subject to further examination by the relevant authorities.
Centre Orders Investigation Into the Cost Revision
The cost controversy has also attracted the attention of the Union Ministry of Environment, Forest and Climate Change.
Satara honorary wildlife warden Rohan Bhate raised concerns about the revised project cost and its potential impact on the conservation contribution. He reportedly submitted complaints through the Prime Minister’s grievance redressal portal and the Maharashtra government’s Aaple Sarkar portal on October 30, 2026.
On November 6, the Union Environment Ministry directed the state forest department to investigate the matter on priority, according to The Indian Express.
The investigation is important because the cost estimate affects the calculation of the conservation contribution. Authorities will need to establish whether the revised amount appropriately represents the project activity for which the wildlife-related contribution is being calculated.
The stop-work order issued on November 13 is a separate regulatory action focused on the alleged absence of prior wildlife approval.
What Happens Next?
The immediate next step is Adani Green’s response to the forest department’s notice. The company has been asked to provide its statutory approvals, project maps and tree-cutting permissions, along with an explanation of the authority under which construction commenced.
The NBWL’s decision on the wildlife-clearance proposal will also be important. Until the relevant authorities resolve the approval question, the project faces uncertainty over when construction can resume.
The cost-revision issue could require a separate examination of the company’s submissions, the basis for the revised figure and the associated conservation contribution.
The Bigger Picture
The Tarali project highlights the regulatory challenges involved in developing large energy infrastructure near ecologically sensitive regions. Pumped-storage facilities can support India’s renewable-energy ambitions by providing electricity when solar and wind generation is unavailable. However, their development must also comply with environmental, forest and wildlife requirements.
The controversy also raises questions about how project costs are reported and how conservation contributions are calculated. For regulators, the challenge is to ensure that infrastructure development and environmental protection proceed under transparent and consistent rules.
Looking Ahead
The project’s immediate future will depend on the forest department’s review of the company’s explanation and the progress of the NBWL approval process. The separate investigation into the revised project cost could also determine whether further regulatory action is necessary. Until these issues are resolved, the 1,500 MW project faces uncertainty over its construction schedule.
For Adani Green, the priority will be to demonstrate that the project has complied with applicable approval requirements and clarify the basis of the two cost figures. For Maharashtra’s authorities, the case will test how environmental safeguards and conservation obligations are enforced while the state pursues additional energy-storage capacity.