State-owned Oil and Natural Gas Corporation (ONGC) has taken over operations and control of the disputed CB-OS-02 offshore oil and gas block in the Cambay basin from Vedanta Oil & Gas Limited following a Delhi High Court ruling. The development marks a significant change in the management of the oil and gas asset, which Vedanta had operated for years. The company has also recognised an impairment charge of approximately ₹379 crore against assets and receivables associated with the block.

The takeover became effective on July 22, 2026, after a single-judge bench of the Delhi High Court dismissed Vedanta’s challenge to the government’s decision not to extend the block’s production-sharing contract (PSC). However, the legal dispute is not over. Vedanta has appealed against the ruling before a division bench of the Delhi High Court, where hearings have concluded and the judgment has been reserved.

ONGC Takes Control of Cambay Offshore Block

ONGC confirmed in its regulatory filing that it assumed custody and operational control of the CB-OS-02 block on July 22, 2026.

The block is located in the Cambay basin off the western coast of India and was previously operated by Vedanta Oil & Gas under a production-sharing arrangement.

Before the takeover, the participating interests in the block were distributed among three companies:

  • Vedanta Oil & Gas Limited: 40%
  • Oil and Natural Gas Corporation: 50%
  • Invenire Petrodyne Limited: 10%

Although ONGC already held the largest participating interest, Vedanta was responsible for operating the block.

Following the court ruling, ONGC took over operations and applied for a petroleum lease on July 28, 2026.

The state-owned company said it had accounted for its interest in the block as an unincorporated joint venture until July 21. From July 22 onward, it began operating the asset under the terms applicable to the government’s nomination regime.

This means operational responsibility has shifted to ONGC even though the legal proceedings involving Vedanta remain unresolved.

Why Did the Government Transfer the Cambay Block?

The dispute centres on the government’s decision not to extend the production-sharing contract for the Cambay block.

The contract expired on June 29, 2023. Before its expiry, Vedanta and its joint venture partners had applied for an extension on June 28, 2021, under the government’s 2017 extension policy.

However, the Ministry of Petroleum and Natural Gas rejected the extension request through a letter dated September 19, 2025.

The government also directed that operations of the block be handed over to ONGC.

Vedanta challenged the decision before the Delhi High Court on September 22, 2025. During the proceedings, the court granted interim relief on June 6, 2026, directing the parties to maintain the existing status quo.

That protection ended on July 22, 2026, when the single-judge bench dismissed Vedanta’s petition. The interim stay was consequently vacated, allowing ONGC to take control of the block.

Vedanta subsequently appealed against the decision before a division bench.

Vedanta Books ₹379 Crore Impairment Charge

The loss of operational control has resulted in a financial impact for Vedanta Oil & Gas.

The company recognised an impairment charge of approximately ₹379 crore during the first quarter of FY27 against assets and receivables associated with the Cambay block.

An impairment charge is an accounting adjustment made when a company determines that the value of an asset or financial balance recorded in its books may no longer be recoverable in full.

Vedanta said the decision was based on the absence of a valid production-sharing contract following the court ruling and uncertainty surrounding the recoverability of assets and receivables linked to the block.

The company also stopped recognising revenue and related expenses from the Cambay block with effect from July 22, 2026.

The impairment reflects the uncertainty surrounding the asset’s future financial benefits. It does not necessarily represent an immediate cash payment of ₹379 crore.

Vedanta has also clarified that the ultimate outcome of the legal dispute and any additional financial consequences cannot currently be determined.

Vedanta’s Appeal Against the Delhi High Court Order

Despite the operational takeover, the legal dispute between Vedanta and the government remains active.

Vedanta has challenged the single-judge bench’s July 22 decision before a division bench of the Delhi High Court.

According to the companies’ regulatory disclosures, hearings in the appeal concluded on October 1, 2026, and the matter has been reserved for judgment.

The outcome could have implications for the company’s claims relating to the extension of the production-sharing contract and its interests in the disputed block.

However, the appeal has not yet resulted in a reversal of the operational takeover. ONGC continues to operate the block under the applicable nomination regime.

The final legal decision could also influence how the parties address the financial consequences of the dispute.

Who Will Bear Future Liabilities of the Cambay Block?

ONGC has provided details about how liabilities associated with the block will be handled following the transfer of operations.

According to its regulatory filing, decommissioning liabilities will be met through the site restoration fund maintained for the block.

Decommissioning refers to the process of safely closing oil and gas infrastructure when it reaches the end of its useful life. This can involve removing equipment, securing wells and restoring the affected site.

ONGC also stated that other future liabilities arising from petroleum operations after the takeover would be borne by the state-owned company for as long as it continues to operate the block.

This clarification is important because the transfer involves not only operational control but also responsibility for ongoing activities and associated obligations.

The arrangement provides greater clarity on how future operating liabilities will be managed while the legal dispute continues.

What the Takeover Means for ONGC

The takeover gives ONGC direct operational control of the Cambay block, allowing the state-owned energy company to manage petroleum operations under the nomination regime.

The company already held a 50% participating interest in the asset, making it the largest existing stakeholder before the change in operatorship.

Taking over operations could give ONGC greater control over production planning, technical decisions and future development activities.

However, the commercial significance of the takeover will depend on the block’s production potential, operating costs, remaining reserves and the investments required to maintain or increase output.

The regulatory disclosures do not establish how much additional production or revenue ONGC expects from the asset.

For Vedanta, the immediate impact is the loss of operational control and the recognition of the ₹379 crore impairment charge. The company’s future position will depend partly on the outcome of its pending appeal.

The Bigger Picture

The Cambay block dispute highlights the importance of production-sharing contracts in India’s oil and gas industry. These agreements determine how private and public-sector companies explore, develop and operate hydrocarbon assets.

The government’s decision not to extend Vedanta’s contract, followed by the judicial ruling and ONGC’s takeover, demonstrates how regulatory decisions and contractual disputes can significantly affect long-term energy investments.

For investors, the case also highlights the importance of evaluating legal risks associated with natural-resource businesses. A company’s ownership interest in an asset does not necessarily guarantee continued operational control or future revenue.

Looking Ahead

The next major development will be the division bench’s judgment on Vedanta’s appeal. Until then, ONGC will continue operating the CB-OS-02 block under the nomination regime, while Vedanta has stopped recognising revenue and related expenses from the asset following the July 22 ruling.

The financial implications for both companies will depend on the final legal outcome, the recoverability of Vedanta’s remaining assets and receivables, and ONGC’s ability to manage the block’s operations. The ₹379 crore impairment is an immediate accounting consequence, but the broader commercial and legal impact remains uncertain.