Uttar Pradesh is targeting more than ₹2 lakh crore in investments and over 2 gigawatts (GW) of additional data centre capacity under its Data Centre Policy 2026. The state government is offering financial incentives, land subsidies and electricity-related exemptions to attract large-scale data centre operators, cloud infrastructure companies and investors developing artificial intelligence (AI) computing facilities. The policy also aims to encourage Tier III and Tier IV-certified data centres and expand the use of renewable energy.
The policy was approved by the Uttar Pradesh Cabinet on July 6, 2026, and subsequently notified by the state government. It replaces the earlier Data Centre Policy 2021 and reflects the growing importance of data storage and computing infrastructure as demand for AI, cloud services, digital payments and online platforms increases. Uttar Pradesh wants to establish itself as a major digital infrastructure destination, but achieving its investment target will depend on converting proposed projects into operational data centres.
Key Takeaways
- Uttar Pradesh is targeting more than ₹2 lakh crore in data centre investments.
- The policy aims to add more than 2 GW of data centre capacity.
- Data Centre Parks can receive interest subsidies of up to ₹50 crore.
- Individual Data Centre Units can receive capital subsidies of up to ₹20 crore.
- Land subsidies range from 25% to 50%, depending on the region.
- Eligible investors can receive a 100% electricity duty exemption for 10 years.
- The state wants new data centres to source 50% of their energy requirements from renewable sources by 2030.
- Additional incentives support AI computing infrastructure and green certifications.
- The policy covers large data centre parks, individual facilities and edge data centres.
What Is Uttar Pradesh’s Data Centre Policy 2026?
The Uttar Pradesh Data Centre Policy 2026 is a state-level framework designed to attract investment in digital infrastructure.
Data centres are specialised facilities that house computer servers, storage systems, networking equipment and supporting infrastructure. They store, process and distribute information used by businesses, governments and consumers.
Every time someone makes a digital payment, streams a video, accesses cloud storage or uses an AI application, data centre infrastructure helps process the underlying information.
The rapid growth of generative AI and cloud computing is increasing demand for facilities with substantial computing power, reliable electricity, advanced cooling systems and high-speed connectivity.
Uttar Pradesh wants to attract companies building this infrastructure by reducing the cost and complexity of setting up data centres.
The new policy replaces the state’s 2021 framework and raises its investment and capacity ambitions.
| Policy target | Government ambition |
|---|---|
| Investment | More than ₹2 lakh crore |
| Additional data centre capacity | More than 2 GW |
| Renewable energy target | 50% of new data centre energy requirements by 2030 |
| Data centre standards | Focus on Tier III and Tier IV facilities |
These are policy targets, not confirmed investment receipts or completed infrastructure.
Major Financial Incentives for Data Centre Investors
Building a data centre requires substantial upfront capital.
Investors must acquire land, construct specialised buildings, install servers and networking equipment, arrange power infrastructure and establish cooling systems.
Uttar Pradesh’s policy offers several incentives to reduce these costs.
1. Interest Subsidy of Up to ₹50 Crore
Eligible Data Centre Parks can receive an interest subsidy of up to ₹50 crore.
The incentive is intended to reduce the financing burden on developers establishing large data centre campuses.
Data centre parks generally involve substantial infrastructure investments and can accommodate multiple facilities or operators.
2. Capital Subsidy of Up to ₹20 Crore
Individual Data Centre Units can receive a capital subsidy of up to ₹20 crore.
This is designed to support companies establishing standalone data centre facilities rather than only large multi-unit parks.
The distinction allows the policy to support different investment models and project sizes.
3. Land Subsidies of Up to 50%
Land costs can be a major component of data centre development.
The policy offers different land subsidy levels depending on the region:
| Region | Land subsidy |
|---|---|
| Madhyanchal | 25% |
| Paschimanchal | 25% |
| Bundelkhand | Up to 50% |
| Poorvanchal | Up to 50% |
The higher subsidy in Bundelkhand and Poorvanchal is intended to encourage investment beyond the state’s more established industrial and commercial centres.
This could help distribute digital infrastructure development across a wider geographical area.
4. Electricity Duty Exemption for 10 Years
Data centres consume substantial amounts of electricity because servers and networking equipment operate continuously.
They also require cooling systems to maintain suitable operating temperatures.
Under the policy, eligible data centre units can receive a 100% electricity duty exemption for 10 years, subject to the applicable conditions.
This can reduce operating expenses over the initial years of a project.
5. Stamp Duty and Renewable Energy Benefits
The policy provides a 100% stamp duty exemption on eligible land purchased or leased from government authorities.
It also offers exemptions on transmission and wheeling charges for renewable electricity, with the applicable benefit depending on the source of power and policy conditions.
These provisions are intended to make it easier for operators to arrange land and access renewable electricity.
Policy Encourages AI Computing and High-Performance Infrastructure
Artificial intelligence is becoming an important driver of data centre investment.
Training and operating advanced AI models requires substantial computing resources, including specialised processors, high-speed networking and advanced cooling infrastructure.
Traditional data centres primarily designed for conventional enterprise workloads may not be sufficient for every large-scale AI application.
Uttar Pradesh’s policy therefore includes additional support for AI computing infrastructure.
Eligible Data Centre Parks with at least 700 FP64 AI Compute Units can qualify for an additional interest subsidy of ₹2 crore annually, subject to an overall additional ceiling of ₹10 crore.
The incentive is intended to encourage investment in high-performance computing facilities.
The policy also supports AI research clusters, high-performance computing and innovation ecosystems.
For the state, attracting such facilities could create opportunities across several connected industries, including semiconductor infrastructure, networking, cloud services, cybersecurity and specialised engineering.
Focus on Green Data Centres and Renewable Energy
Electricity consumption is one of the biggest operational challenges for data centres.
Large facilities need continuous power to operate servers, storage equipment, cooling systems and networking infrastructure.
As the number of AI workloads increases, electricity demand could become an even more important factor in data centre expansion.
Uttar Pradesh’s policy aims to address this challenge by encouraging renewable energy adoption.
The government wants new data centres to meet 50% of their energy requirements through renewable sources by 2030.
The policy also provides additional incentives linked to green certification, power usage effectiveness and renewable energy consumption.
Eligible projects can receive additional interest subsidy benefits, with a maximum increase of ₹2 crore annually and ₹10 crore overall under the specified provisions.
The broader objective is to attract investment while encouraging more energy-efficient digital infrastructure.
However, renewable energy targets will require sufficient power generation, transmission capacity and arrangements for reliable electricity supply.
Which Data Centre Projects Qualify Under the Policy?
The policy separates projects into categories based on their size and power requirements.
This allows Uttar Pradesh to support large data centre campuses as well as smaller facilities located closer to users.
| Project category | Eligibility requirement |
|---|---|
| Data Centre Park | Minimum total load of 40 MW |
| Data Centre Unit | More than 2 MW and less than 40 MW |
| Edge Data Centre | At least 10 sites, each with a minimum 50 kW capacity and a combined load of at least 2 MW |
Data Centre Parks are intended for large-scale infrastructure development.
Individual Data Centre Units can be established as standalone facilities or within larger parks.
Edge Data Centres are smaller facilities designed to process information closer to consumers, businesses and connected devices.
This can help reduce latency and support applications that require faster responses.
The policy also provides support for Centres of Excellence, which can help strengthen research, innovation and technical capabilities in the data centre ecosystem.
How Much Investment Has Uttar Pradesh Attracted So Far?
The new policy builds on the state’s earlier efforts to attract data centre developers.
Under the 2021 policy, Uttar Pradesh had targeted ₹20,000 crore in investment and 250 MW of data centre capacity.
According to figures published by the state government for June 2025, the earlier framework had recorded:
| Indicator | Progress under earlier framework |
|---|---|
| Proposed investment | ₹21,342.90 crore |
| Proposed data centre capacity | 644 MW |
| Memorandums of Understanding | 29 |
| Commercialised data centre projects | 7 of 8 listed |
| Commercialised capacity | 133 MW |
The figures show that proposed investment and capacity were substantially higher than the original targets.
However, proposed investment, signed agreements and operational capacity are different measures.
An MoU represents an investment intention and does not establish that the entire project has been financed, constructed or commissioned.
The distinction will be important when assessing progress under the 2026 policy.
Greater Noida Emerges as an Important Data Centre Investment Location
Greater Noida is among the locations attracting attention from data centre developers.
In January 2026, Uttar Pradesh signed an agreement with AM Green for a proposed 1 GW data centre project in Greater Noida.
The project was associated with a proposed investment of $25 billion.
If implemented as planned, it would represent a major addition to the state’s digital infrastructure ambitions.
However, the proposed investment and capacity should not be treated as an operational facility or completed capital expenditure.
Large data centre projects require land development, power arrangements, construction, equipment procurement and commissioning.
Their progress will depend on execution and the availability of supporting infrastructure.
Why Uttar Pradesh Wants to Become an AI and Data Centre Hub
The expansion of artificial intelligence, cloud computing and digital services is increasing demand for data centre capacity across India.
Companies need infrastructure to store information, process transactions, operate applications and run increasingly complex AI workloads.
Uttar Pradesh is attempting to attract a larger share of this investment by combining financial incentives with land availability and infrastructure support.
The state’s large consumer market and industrial base could also create opportunities for cloud providers, enterprise technology companies and digital service operators.
Data centre development can generate demand for several supporting industries:
- Construction and industrial engineering.
- Electrical equipment and power distribution.
- Cooling and thermal management systems.
- Telecommunications and fibre connectivity.
- Cybersecurity and cloud services.
- Renewable energy generation.
- Facility management and technical maintenance.
The potential economic impact therefore extends beyond the data centre operators themselves.
However, investors will evaluate more than subsidies when selecting locations. Reliable electricity, water availability, connectivity, land readiness, regulatory approvals and operating costs will all influence project decisions.
The Bigger Picture: India’s Competition to Build AI Infrastructure
Uttar Pradesh’s policy is part of a wider competition among Indian states to attract data centre investment.
Maharashtra has an established data centre ecosystem, particularly around Mumbai and Navi Mumbai. Tamil Nadu is also positioning itself for additional digital infrastructure investment.
Uttar Pradesh is using a more aggressive incentive-led approach to attract new capacity and strengthen its position in the national market.
The opportunity is growing because AI infrastructure requires significantly more computing power than many conventional digital applications.
At the same time, data centres create challenges involving electricity consumption, cooling requirements, water use and environmental sustainability.
The success of Uttar Pradesh’s policy will therefore depend on whether it can combine investment incentives with reliable infrastructure and sustainable operations.
The ₹2 lakh crore target is ambitious, but the more important measure will be how much investment reaches construction and how much capacity eventually becomes operational.
What Happens Next?
The next stage will involve converting the policy framework into investment commitments, project approvals and construction activity. Data centre developers will assess the available subsidies, land options, power infrastructure and eligibility requirements before making investment decisions. The state government’s progress will need to be measured through actual capital deployment, construction milestones and commissioned capacity rather than announced investment targets alone.
Uttar Pradesh will also need to demonstrate that it can provide reliable electricity, renewable power access, connectivity and other infrastructure required by large computing facilities. The 2030 renewable energy target and the proposed expansion of AI-ready capacity will be important indicators of execution. The policy creates a financial framework to attract investors, but long-term success will depend on the state’s ability to turn those incentives into commercially viable and operational data centres.
Frequently Asked Questions (FAQs)
1. What is the Uttar Pradesh Data Centre Policy 2026?
It is a state government policy designed to attract investment in data centres, AI computing infrastructure and digital services through financial incentives, land subsidies and electricity-related benefits.
2. How much investment does Uttar Pradesh want to attract?
The state is targeting more than ₹2 lakh crore in data centre investments.
3. How much data centre capacity does the policy target?
The policy aims to add more than 2 GW of additional data centre capacity.
4. What subsidy is available for Data Centre Parks?
Eligible Data Centre Parks can receive an interest subsidy of up to ₹50 crore.
5. What subsidy is available for individual Data Centre Units?
Eligible individual Data Centre Units can receive a capital subsidy of up to ₹20 crore.
6. What land subsidies are available?
The policy offers 25% land subsidies in Madhyanchal and Paschimanchal and up to 50% in Bundelkhand and Poorvanchal.
7. Does the policy offer electricity tax benefits?
Yes. Eligible Data Centre Units can receive a 100% electricity duty exemption for 10 years, subject to policy conditions.
8. What is the renewable energy target?
The state aims for new data centres to meet 50% of their energy requirements through renewable sources by 2030.
9. What is the minimum capacity for a Data Centre Park?
A Data Centre Park must have a minimum total load capacity of 40 MW under the policy.
10. What is an Edge Data Centre?
An Edge Data Centre is a smaller computing facility located closer to users and connected devices. It can help process information faster and reduce latency.
11. When was the Uttar Pradesh Data Centre Policy 2026 approved?
The Uttar Pradesh Cabinet approved the policy on July 6, 2026. The state subsequently notified the policy and published its guidelines.
12. Has Uttar Pradesh already received ₹2 lakh crore in investment?
No. More than ₹2 lakh crore is the policy’s investment target. It should not be confused with money already received or projects already completed.